Next Article in Journal
Morphological Foot Model for Temperature Pattern Analysis Proposed for Diabetic Foot Disorders
Next Article in Special Issue
A Thermal Discomfort Index for Demand Response Control in Residential Water Heaters
Previous Article in Journal
A Screw-Axis Approach to the Stability of Two-Wheeled Vehicles
Previous Article in Special Issue
Exact and Evolutionary Algorithms for Synchronization of Public Transportation Timetables Considering Extended Transfer Zones
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Battery Energy Storage System Dimensioning for Reducing the Fixed Term of the Electricity Access Rate in Industrial Consumptions

Centro de Investigaciones Energéticas, Medioambientales y Tecnológicas (CIEMAT), Government of Spain, 28040 Madrid, Spain
*
Author to whom correspondence should be addressed.
Submission received: 30 June 2021 / Revised: 3 August 2021 / Accepted: 6 August 2021 / Published: 11 August 2021

Abstract

:
Industrial buildings account for very few high peaks of power demand. This situation forces them to contract a high fixed electricity term to cover it. A more intelligent use of the energy in industrial buildings, together with an improved efficiency of the transmission and distribution of the energy along the electric power grid, can be achieved by reducing the peak consumption of industrial buildings. Energy storage systems, and lithium ion (Li-ion) batteries in particular, are one of the most promising technologies for reducing this peak consumption. However, selecting a proper Li-ion battery requires a dimensioning process in terms of energy and power which is not straightforward. This paper proposes a dimensioning methodology that takes into consideration both technical and economic implications, and applies it to a case example with real industrial consumption data and a commercial battery. Results show that implementing batteries for reducing this peak consumption can lead to a cost–benefit improvement.

1. Introduction

The fee that electric energy consumers pay for being able to make use of it, commonly known as electricity access rate, is split into two terms in the majority of European countries: a variable term and a fixed term [1]. The variable term is associated with the energy consumed by the user (kWh), while the fixed term corresponds to the contracted power (kW), defined as the maximum power that the user can consume before the power-limit switch is triggered.
Commonly, the fixed term is over-dimensioned, meaning that the usual consumption along a day is considerably lower than the power consumption limit, the latter being reached only during a few instants per day. This behaviour is specially representative of industrial consumption, forcing them to contract a high fixed electricity term due to very few high power consumption peaks [2].
Modifying this electrical consumption pattern could lead to a more intelligent use of the energy in industrial buildings, to the fostering of the “prosumer” behaviour among industrial consumers, and to the improvement of the efficiency of transmission and distribution of the electricity across the power grid. Among the different solutions proposed in the literature for achieving this goal, the inclusion of photovoltaic panels is presented as a feasible solution in [3,4], although the vast majority of studies opt for implementing an energy storage system (ESS) so that the joint consumption profile of the ESS and the industrial building is modified, as in [5,6,7] among other studies.
Battery energy storage systems (BESS) arise as the most promising ESS candidates for their connection in buildings and infrastructures, both industrial and residential, considering that this is one of their most prominent and leading uses [8]. The benefits of including BESS encompass the majority of the electricity value chain, including peak shaving and continuity of supply for residential and industrial customers, ancillary and power quality services for transmission and distribution system operators, and flexibility and curtailment minimization for renewable generation companies [9].
Nevertheless, selecting a BESS for its connection to an industrial consumption for reducing the peak power consumption is not straightforward. A wide variety of solutions is offered by battery manufacturers, so a dimensioning process based on a techno-economic assessment is required in order to help decision makers. This techno-economic assessment will incorporate the load characteristics, the BESS technical features and its cost.
In this regard, BESS dimensioning for reducing the electricity access fee in industrial buildings has been studied together with photovoltaic in [10,11], where a dimensioning process is proposed for a BESS and photovoltaic installation by using a brute force methodology, and applied to peak shaving and prosumer purposes, and for working isolated from the grid. In addition, the authors in [12] analyse the economic viability of BESS integration under different tariff structures and systems configurations, although a generalized and simplified ageing for the Li-ion BESS has been assumed for the yearly cost calculations. Thus, the importance of the BESS charge/discharge profile has not been taken into account properly. A similar approach is proposed in [13,14] for residential consumption. Both papers assess the economic viability of integrating BESS at a residential level with and without subsidies. However, these studies lack a detailed analysis of the BESS lifespan, since they neglect its influence in the overall yearly costs. Further studies, such as [15], analyse the peak shaving of decentralised residential BESS for load peak shaving. The proposed BESS model includes the battery efficiency and SoC estimation, but an over-simplified battery ageing assumption is made, where the payback period of the battery varies linearly with the battery size.
Regarding alternative dimensioning methodologies, stochastic models for improving the decision making are developed in [16], where the methodologies are applied to reach the optimal BESS investment for industrial buildings. As identified in the previously mentioned papers, there is no detailed battery ageing analysis, so the influence of this variable is underestimated.
The BESS dimensioning studies mentioned above employ different selection criteria. Those criteria are based only on technical issues, or on techno-economic issues but using generic ageing data to calculate the BESS lifespan. Moreover, they analyse the complete compensation of technical issues under study, e.g., feed an isolated load with a combination of a BESS together with photovoltaic or eliminate the consumption peaks via smart charging of electric vehicles, which may not be the most feasible scenario faced by residential or industrial consumers. As a main contribution and further development, this paper proposes a BESS dimensioning methodology for diminishing the fixed term of the electricity access rate in real industrial consumption, employing a techno-economic criterion for selecting the optimum solution. The proposed methodology includes a detailed evaluation of the BESS ageing, which is included in the cost–benefit analysis as a key component. This improved BESS ageing assessment highly influences the time for a BESS replacement and, hence, the yearly cost (BESS cost and fixed electricity access fee).
Hence, the applicability of this methodology encompasses industrial consumers with an irregular consumption accounting for several peaks of consumption, as well as BESS manufacturers aiming for specific developments for industrial consumption. The applicability of the developed methodology is exemplified in this paper for an existing industrial consumption and on a typical day in summer and in winter, considering a commercial battery and standard prices for the economic analysis.
The paper is organized as follows: the BESS dimensioning methodology is described in Section 2, including a series of steps to be followed. The different simulation models used along the different steps determined by methodology are detailed in Section 3, including a power grid model, an industrial consumption model, a power converter model, and a battery model. At last, a case example with real industrial consumption data, commercial BESS and standard prices is presented in Section 4, while conclusions are drawn in Section 5.

2. BESS Dimensioning Methodology

The BESS dimensioning methodology described in this section aims at reducing the fixed term of the electricity access rate by introducing a BESS that deals with the peaks of the industrial consumption. A few assumptions made by the authors in the development of the BESS dimensioning methodology are presented in the following.
Firstly, both the BESS ( P B E S S ) and the electrical grid ( P G R I D ) must cover the customers’ demand ( P L O A D ) and the losses ( P L O S S ):
P B E S S + P G R I D = P L O A D + P L O S S
Moreover, the BESS must account for enough energy to cover the energy to fulfill the extra energy demand not supplied/covered by the grid. Besides, a BESS must be able to fully recharge the same amount of energy as dispatched in a specific scenario. If not, the mean SoC will be decaying as the scenario repeats over time, being eventually unable to fulfil the load power demand.
The methodology comprises a set of steps, as seen in the flow chart of Figure 1.
  • Step 1: Models parameterizations. The different models, which are mathematical representations of physical systems or devices, account for variables (inputs and outputs) and parameters. In order to particularize the models (grid, BESS, and industrial consumption) to a specific system or device, those parameters must be adjusted to a fixed value.
  • Step 2: Define test cases. The variable that defines the test cases is the maximum fixed power that the grid can deliver ( P L I M I T ). Reducing this power limit implies adding a greater contribution from the BESS, which yields to the different scenarios, which consequently will result in different BESS configurations and different BESS ageing.
  • Step 3: Simulate test case, calculate BESS requirements, and BESS configuration. Once the scenarios have been defined, a simulation is performed for every value of P L I M I T . Each scenario implies different necessities from the BESS, regarding power and energy. This requirements give different BESS configurations, in terms of number of cells in series and in parallel. The charge/discharge profile for the BESS is also obtained from the simulation. If the energy available for charging is unable to match the amount of energy dispatched by a BESS in a specific scenario, that scenario will not be considered for the dimensioning process. As previously noted, this situation will force the BESS to, eventually, not being able to feed the load when the scenario repeats over time.
  • Step 4: Calculate BESS ageing. Once the minimum BESS configuration that satisfies the power and energy requirements is selected for each scenario, a BESS ageing analysis is performed, based on the BESS model and configuration, and on the charge/discharge profile for each specific scenario. As a result of this step, the number of days until the BESS loses a 20% of capacity retention is obtained.
  • Step 5: Cost–benefit analysis. Prices and fees for both a BESS (as a function of the kW and kWh of the system) and the fixed access power are needed for their incorporation into a cost function. BESS standard prices as well as Spanish fixed access rates are provided in Section 4, with a case example. The cost can be computed yearly, taking into account the net present cost, and the capital recovery factor. The base scenario, i.e., when there is no BESS, is then compared to the rest of scenarios in terms of cost, and the final solution can be chosen.

3. Industrial Consumption, BESS, and Grid Modelling

The mathematical and simulation models used in Section 4 for performing a case example of the aforementioned methodology are described in this section. Three main models are considered: an industrial consumption, a BESS, and a power grid. The BESS is connected to the same point as the industrial consumption, the point of common coupling (PCC), and both of them are connected to the grid, as it can be seen in the general model diagram in Figure 2. The complete model outputs several electrical-variables time series (P, Q, V, and I) for the three main components. Additional electrical variables such as frequency or harmonic distortion are also evaluated and calculated by the model, but the authors decided not to output them since they are not relevant for the purpose of this paper.
The models are developed with MATLAB Simulink, under the Simscape Electrical environment. When developing simulation models, a higher complexity and completeness usually implies a higher accuracy [17,18]. However, complex models tend to require a substantial computational effort to run them, and a huge amount of information to parametrize them. Moreover, they are commonly valid only for a specific device, making them non-generalizable [19,20].
On the other hand, simplified models, usually composed by combination of resistors, inductors, and capacitors, are easily parametrized, they require low computational effort, and are valid for several devices with similar characteristics. Furthermore, even though they are not as accurate as complex models, they can mimic the behaviour of the device with sufficient precision, allowing for the extraction of general conclusions [21,22].
Hence, given the objective of this paper, the approach taken by the authors was to develop simplified models, that are generalizable and easily parametrized, which is sufficient for obtaining accurate general conclusions when dimensioning BESS.

3.1. Industrial Consumption Model

The industrial consumption is modelled as a PQ load, i.e., it consumes the desired active and reactive power independently of the voltage at the PCC. Hence, it needs to be modelled as a controlled current source, as depicted in Figure 3. The inputs of the model, named as P and Q in Figure 3, correspond to the 24-hour active and reactive power profile on a 1-second basis.
The Simulink diagram in Figure 3 shows, from left to right, the inputs of the model P and Q together with the measured voltage (Vabc). From those inputs, the complex values of the phase currents are calculated, and then redirected to the corresponding current controlled source. A resistor with a very high value is also connected in parallel, which acts as a snubber. At last, the industrial consumption model is linked to the rest of the model via connectors A, B, C, and N.

3.2. BESS Model

The BESS model includes both a battery model and a power electronic converter model, the latter being necessary to manage the battery behaviour and to connect the battery to the AC grid.

3.2.1. Electronic Converter Model

For the purpose of this work, there is no need to model the power electronic converter in detail, since neither efficiency nor power converter ageing are incorporated into the economic evaluation of the methodology. Thus, an ideal voltage source converter (VSC) has been selected, with no conduction or switching losses and no power limitations, so the battery can dispatch as much power as required. As a result, the VSC is modelled as a controlled three-phase voltage source whose reference voltage is given by the converter control, which manages the power that flows in and out of the battery.
The control of a VSC can be modelled as explained in [23], consisting of two levels: a high-level control and a low-level control. The high-level control is in charge of selecting, based on a specific strategy, the power dispatched or consumed by the battery. Several strategies have been proposed in the literature, from those based on rules [24] to more complex strategies [25,26]. For this paper, a simple strategy based on rules has been selected, which sets the reference power for the battery ( P B A T T ) based on the maximum power that the industrial consumption can absorb from the grid ( P L I M I T ), the actual power that the industrial load is demanding ( P L O A D ), and the battery state of charge ( S o C B A T T ). The flow diagram for the high-level control is shown in Figure 4.
The BESS recharge profile has been defined as the minimum current that allows the BESS to recharge the same amount of energy that it has provided to the load along the day. Moreover, reactive power reference for the battery has been set to zero, so no contribution is expected from it.
On the other hand, the low-level control is in charge of setting the voltage at the VSC terminals so that the power management commanded by the high-level control can be performed. The low-level control is a dq axis control, shown in Figure 5, which has been developed building on [27]. The control is duplicated for P and Q, with minor variations. Each branch accounts for an outer PI loop control, which sets the battery power equal to the reference power coming from the high-level control, outputting a reference current. Then, there is an inner PI loop control that adjusts the current flow through the VSC with the reference current, so a reference voltage is outputted. This voltage is finally regulated so that it corresponds to the VSC voltage at its terminals. In order to properly control the VSC, the inner control must be considerably faster than the outer control. Detailed explanation about the implemented dq axis control for a VSC can be found in [23,27].

3.2.2. Battery Model

The battery model controlled by the VSC is represented as an equivalent circuit model which, as mentioned above, sacrifices accuracy in favour of generality. Nevertheless, equivalent circuit models account for errors lower than 5% [28], sufficient for obtaining general conclusions. The battery equivalent circuit is depicted in Figure 6, where u is the instantaneous battery voltage [V], i is the battery current [A] (i > 0 discharging; i < 0 charging), I S E L F is the self-discharge current, R O H M is the ohmic internal resistance [ Ω ], R P O L is the polarization internal resistance [ Ω ], and C P O L is the polarization capacitor [F].
The selected battery model has been developed and validated by the authors in [18,29]. The model comprises three parts: a voltage/runtime model, a thermal model, and an ageing model.

Battery Voltage/Runtime and Thermal Model

The lithium-ion battery model used in this paper is a modification of the MATLAB Simulink model in [30]. The battery equivalent circuit is based on the Shepherd equation [31], which was experimentally validated later in [32]. The Shepherd model keeps the error between 1% and 5% and it can be parametrizable without testing the battery in the laboratory: it suffices with the manufacturer datasheet information. For the work developed in this paper, both voltage/runtime and thermal models have been parametrized via a least-square method. Data can be obtained from typical manufacturer’s curves: voltage-capacity curve as a function of different C rates (with constant temperature), and voltage-capacity curve at different temperatures (with constant C rate). The detailed parametrization process is described in [33]. The voltage/runtime equations that govern the model, considering thermal dependencies, can be written as follows:
E ( S o C , T ) = E 0 ( T ) K ( T ) · Q M A X ( T ) · ( 100 S o C 1 ) + A · e ( B · Q M A X ( T ) · ( 1 S o C 100 ) )
R P O L D I S C H A R G E ( S o C , T ) = K ( T ) · 100 S o C
R P O L C H A R G E ( S o C , T ) = K ( T ) · 1 1.1 S o C 100
E 0 ( T ) = E 0 ( T 0 ) d E d T · ( T T 0 )
Q M A X ( T ) = Q M A X ( T ) d Q d T · ( T T 0 )
K ( T ) = K ( T 0 ) e α · ( 1 T 1 T 0 )
R O H M ( T ) = R O H M ( T 0 ) e β · ( 1 T 1 T 0 )
where E is the open-circuit nonlinear voltage (V), E 0 is the open-circuit constant voltage (V), K is the polarization parameter (Ah 1 ), Q M A X is the maximum capacity (Ah), A is the exponential voltage constant (V), B is the exponential capacity constant (Ah 1 ), T is the temperature (K), T 0 is the parameter reference temperature (K), and S o C is the state of charge (%).
The thermal model comprises two different parts: a heat generation model and a heat evacuation model. The heat generation model can be expressed as follows [34]:
H = ( E 0 E ) · i + T · d E d T · i + ( R O H M + R P O L ) · i 2
where H is the generated heat (W), and d E / d T the change of the equilibrium potential with temperature (V·K 1 ).
The heat evacuation model occurs due to convection and radiation mechanisms, the latter being negligible [35]. Assuming that the temperature in the battery is uniform (reasonable approximation according to [36]), the following expression is obtained [35]:
H = m · c p · d T d t + 1 R O U T · ( T T 0 )
R O U T = 1 h · A r
where m is the mass of the battery (kg), c p is the specific heat capacity (J·kg 1 · K 1 ), h is the convective heat transfer coefficient (W·m 2 · K 1 ), A r is the external surface area (m 2 ), and R O U T is the equivalent thermal resistance with the ambient (K·W 1 ).
Hence, the temperature variation can be calculated as:
T ( s ) = H · R O U T + T 0 1 + m · c p · R O U T · s = H · R O U T + T 0 1 + t t h · s
where t t h is the thermal time constant (s), and s is the Laplace complex frequency parameter.

Battery Ageing Model

The ageing estimator implemented in the battery model comprises two parts: a cycling ageing model and a calendar ageing model. In order to parametrize both models, a least-square method has been applied, so the error between the model output and the real battery data is minimized. The data for parametrizing the models need to be obtained from experimental tests. The complete parametrization process is detailed in [33]. A minimum set of 4 tests at different SoC and temperature are needed for the calendar ageing, and a minimum of 5 tests with different combinations of C rate, DoD and temperature are needed for the cycling model. Cycling ageing is related to the capacity fade when the battery is subject to charging and discharging cycles, i.e., when the current is flowing through the battery. It depends on several factors, among which C r a t e , temperature, and DoD are the most relevant [37]. The cycling ageing model published in [38] for lithium-ion batteries has been implemented:
Q l o s s c y c = ( a · T 2 + b · T + c ) · e ( d · T + e ) · C r a t e · A h
where Q l o s s c y c is the cycling loss capacity (Ah), A h the Ah that have flown through the battery (in or out), and a, b, c, d, and e are constants depending on the battery chemistry.
On the other hand, calendar ageing is related to the capacity fade in the battery because of the time passed from the moment it was manufactured. It is dependent on the S o C of the battery, the temperature, and the time [37]. The calendar ageing model published in [39] has been implemented:
Q l o s s c a l = f · e g · S o C · e h T · t z
where a, b, and c are constants that depend on the battery chemistry, and z can take values between 0.5 and 1 and depends on the chemistry as well.
Apart from the ageing factors previously mentioned, additional ageing factors such as DoD or mean SoC along a cycle are indirectly considered by the model. The Ah dependency included in the cycling ageing is indirectly considering the DoD, since the higher the DoD the higher the Ah that flow through the battery. Moreover, the mean SoC along a cycle is considered in the calendar ageing equation, since the latter is constantly computing the battery SoC contribution.

3.3. Grid Model

The grid is modelled as an infinite power grid, so both the frequency and voltage at the PCC are kept constant. A Three-Phase Source model has been selected for this purpose, with a swing generator type, high short-circuit power, and low X/R ratio.

4. Case Example

In order to illustrate how the described methodology could be implemented, a case example is analysed. The models developed in Section 3 are used for performing the simulations. The same structure of steps defined in Section 2 is applied:

4.1. Step 1. Parametrize Models

At first, the simulations models need to be parametrized. For the grid model, the following parameters have been selected, so an almost infinite power grid is implemented (Table 1).
The battery model can be parametrized following the methodology defined in [29,32,33]. A commercial lithium polymer battery cell from Kokam, model SLPB100255255HR2, has been selected for this case study, which is a standard lithium-ion pouch cell [40]. The experimental data for calculating the ageing model parameters have been obtained from [40] and [33], where the complete theoretical and experimental validation for the selected battery cell has been performed. The battery ageing model performs with an error below 5%, as detailed in [33]. The selected battery cell main parameters are shown in Table 2.
The load needs a power consumption profile as input. For this case example, two 24-h profile on a 1-second basis have been selected, corresponding to a typical day in summer and a typical day in winter in an industrial building. The selected building is the CEDEX facility in Madrid, located at Julián Camarillo 30, 28037 Madrid (Spain). For the analysis performed in this paper, the load corresponds to a three-phase load with no unbalance between phases, whose active power profiles are shown in Figure 7 for both summer and winter. The cumulative energy consumed by the load for each typical day is also shown in Figure 8.

4.2. Step 2. Define Test Cases

Test cases are defined by the BESS control parameter, which is the power limit that the load is allowed to consume from the grid ( P L I M T ). Hence, as P L I M I T decreases, the battery will increase its contribution. Scenarios are divided between summer scenarios (S) and winter scenarios (W). SB and WB correspond to the base case scenario for each season, which is the current scenario at the real world facility, with a contracted power of 90 kW. Steps of 10 kW have been selected, so the different scenarios are defined in Table 3.

4.3. Step 3. Simulate Scenarios and Obtain BESS Requirements and Configuration

As previously explained in Section 2 and Section 3, BESSs that are not able to recharge as much energy as they have delivered along the day, are considered as not valid. Once the simulations are performed, BESS power profiles for the valid configurations are obtained. For the case example presented in this paper, valid BESS power profiles are shown in Figure 9 and Figure 10.
As expected, the lower the P L I M I T , the higher the contribution from the BESS. Since the BESS deals with high demand peaks, it follows a similar distribution as the top part of the industrial load profile for the corresponding scenario. Scenarios SB and WB, i.e., when the grid delivers as much power as demanded by the load, implies no contribution from the BESS.
For P L I M I T values below 30 kW, BESSs are not able to recharge the same amount of energy delivered during the high-demand period, both for summer and winter scenarios. It must be noticed that P L I M I T also affects the maximum power available for recharging, i.e., for a P L I M I T value of 20 kW, the maximum power available for recharging is 20 kW since that recharging power is coming from the grid, which is not sufficient for the case with P L I M I T values below 30 kW.
Based on the BESS power profiles, the power and energy requirements ( P B E S S r e q and E B E S S r e q ) for the valid scenarios are shown in Table 4.
Once the requirements are calculated, the most suitable BESS configuration must be selected for each scenario (number of cells connected in series and in parallel). Commercial three-phase inverters for 400 V grids demand 48 V in the DC side. Hence, based on the standard cell parameters, the number of cells in series so the DC side voltage reaches 48 V equals:
48 V D C s i d e v o l t a g e 3.7 V N o m i n a l c e l l v o l t a g e 13
The number of cells in parallel depends on the BESS energy requirements. Given that one branch of 13 cells accounts for:
13 cells · 3.7 V / cell · 55 Ah = 2.64 kWh
The following table can be filled:
Table 4. BESS requirements for the different scenarios.
Table 4. BESS requirements for the different scenarios.
Scenario P LIMIT P BESS req E BESS req Min. BESS Config. E BESS
-[kW][kW][kWh]-[kWh]
SB70---
S6607.130.01513s1p2.64
S55017.130.1213s1p2.64
S44027.132.0713s1p2.64
S33037.1334.7913s14p36.96
WB90---
W8803.450.0113s1p2.64
W77013.450.0513s1p2.64
W66023.450.4313s1p2.64
W55033.4511.5113s5p13.2
W44043.4549.7813s19p50.16
W33053.45101.1413s39p102.96
Scenarios S6 to S4 and W8 to W6 can satisfy their energy requirements with just one BESS branch in parallel. It must be noticed that, given the BESS configuration and the power demand shown in Table 4, the BESS in scenario S4 will be more demanded than in scenarios S5 and S6, and the BESS in scenario W6 will also be more demanded than scenarios W7 and W8, i.e., it will work with higher C rates.

4.4. Step 4. Calculate BESS Ageing

BESS ageing is closely related to its C rate and temperature (among other factors), as previously explained in Section 3. The higher the C rate, the higher the temperature augmentation in the battery. Hence, the BESS configuration has a huge influence on the BESS ageing, since batteries with a higher number of cells in parallel work with lower C rates, i.e., with less stress. This implies that “bigger” BESSs may last longer than “smaller” BESSs, which may be beneficial from a cost–benefit point of view.
Four configurations have been tested for each BESS: the minimum number of cells so that the energy requirements are satisfied, and three more configurations increasing one extra branch each time, so that the C rate is decreased.
Commonly, a BESS is considered as aged when it loses 20% of its capacity retention.
As seen in Figure 11, Scenario S4 presents a very different behaviour from the minimum configuration to the minimum plus one. This happens because the C rate is diminished to a half when the branches in parallel are increased by one (from 1 to 2), which is a big difference according to the ageing model. A higher number of branches in parallel do not improve that much the behaviour, although the ageing is further reduced, as expected.
Scenario S3, which is the summer scenario with more energetic demand from the BESS, does not present a high ageing. This happens because the highest C rates are close to 1C, and there are few moments where those C rates are reached, even though the BESS is dispatching power during longer periods along a day. However, ageing for Scenario S3 is higher than Scenario S6, the BESS is working with a less intermittent profile, implying that temperature is higher during a cycle. Scenario S5 presents a higher ageing that Scenario S3 for the minimum BESS configuration, given that the C rate is higher (close to 3C), although it works for shorter times with that C rate. In any case, a low ageing is expected for every scenario except for Scenario S4.
For winter scenarios, as seen in Figure 12, Scenarios W8 and W7 present a low ageing due to the few periods of time under which the BESS is dispatching power, even though the C rate for W7 and the minimum BESS configuration reaches 5C. Besides, a low ageing is expected for Scenarios W3 and W4 which, being the most energetic form the point of view of the BESS, are hugely over-dimensioned in terms of power (very low C rates).
Scenario W6 presents a similar behaviour as S4, where increasing the number of branches in parallel from 1 to 2 prevents from an excessive ageing, which is produced as a consequence of working with C rates higher than 8C for a few moments along a day. Scenario W5 steadily improves its ageing as the branches in parallel increase, although it suffers from the highest ageing except for the minimum BESS configuration.

4.5. Step 5. Cost–Benefit Analysis

Once the BESS ageing for different configurations and scenarios has been calculated, a cost–benefit analysis must be performed, considering both the BESS cost and fixed term energy cost. Among the different reports found in the literature that analyse energy storage costs, the one published in [41] has been selected as the most reliable study.
Moreover, electricity access fees for industrial consumption for the regulated market in Spain can be found in [42]. The fixed term of the access fee considers three time periods of time-discrimination (P1, P2, and P3). For further information about the Spanish regulated market, and time discrimination periods, the authors recommend the work published in [42].
The variable term of energy is kept constant for every scenario, i.e., the BESS is re-charged from the grid, and the BESS energy recharged form the grid plus the industrial load demand matches the total energy consumed by the industrial load in scenarios SB and WB, so the overall energy consumption remains constant. Hence, it is not included in the cost. Costs are summarized in Table 5 [42].
Considering this, the cost equation can be written as:
C o s t ( e u r o y e a r ) = ( P 1 + P 2 + P 3 ) · P L I M I T + B E S S p r o j e c t c o s t
The contracted power ( P L I M I T ) is considered constant for the three time-discrimination periods (as is requested to industrial consumption).
The yearly BESS project cost has been calculated based on [43,44,45]. The annualized cost of the BESS project has been defined as:
C a n n = C R F ( i , R p r o j ) · C N P C
where C a n n is the annualized cost, C N P C is the net present cost, and C R F is the capital recovery factor, which depends on the annual real discount rate (i) and on the project lifetime ( R p r o j ). C N P C is calculated as the present value of all the costs of installing and operating the battery over the project lifetime, minus the present value of all the revenues earned over the project lifetime.
Hence, the total yearly cost is calculated as follows: -4.6cm0cm
C o s t ( e u r o y e a r ) = ( P 1 + P 2 + P 3 ) · P L I M I T + C a n n = ( P 1 + P 2 + P 3 ) · P L I M I T + C R F ( i , R p r o j ) · C N P C
The constants for calculating the BESS project cost are listed in Table 6 [41,43],
Table 6. Summarized costs for the BESS project.
Table 6. Summarized costs for the BESS project.
ItemValue [Unit]
BESS cost (€/kW)1876 €/kW
BESS cost (€/kWh)469 €/kWh
C O M 10 €/kW and year
i3.41%
N p r o j 25 years
where C O M is the operation and maintenance cost, and N p r o j is the number of years over which the cost is annualized. The total cost for each scenario is shown in Table 7 and Table 8, where:
T o t a l ( e u r o y e a r ) = F i x e d a c c e s s f e e + B E S S p r o j e c t
As it can be seen in Table 7 and Table 8, results indicate that introducing a BESS into an industrial consumption for diminishing the fixed term of the electricity fee, can reduce the overall yearly cost. Moreover, this reduction can enhance an intelligent use of the energy in industrial buildings, as well as the improvement of the energy efficiency along the electric power grid, since consumption peaks are eliminated.
Table 7 and Table 8 show that the minimum reduction in the fixed power limit is the best solution for this particular case example, both for summer and winter, from the point of view of the industrial consumer. Every configuration in scenario S6, and two of them in Scenario S5, reduce the yearly price of having a higher contracted power in summer. A similar behaviour is obtained in Table 8 for Scenarios W8, W7 and W6. The rest of the scenarios do not improve the yearly cost for this case example, although some interesting conclusions can be drawn.
Scenario S4 shows that the minimum configuration might not be the optimal solution, since configuration 13s2p provides a higher cost reduction than the minimum BESS configuration. A higher number of branches in parallel allows for a reduced C-rate, DoD, and temperature in each scenario. Hence, the BESS lifespan is extended and a higher cost reduction is achieved. A similar result would be expected for Scenario W6, given the ageing behaviour shown in Figure 12. However, in this case, the ageing is sufficiently low with the minimum BESS configuration, so the extra benefit of the further reduction in ageing does not improve that much the yearly cost.
Costs are not reduced in scenarios S4, S3, W5, W4, and W3 with respect to the base case scenario, since the BESS is dedicated not only to reducing the peak consumption, but to dealing with an important part of the load demand. This forces an over-dimensioning in the BESS’s number of cells in parallel (given that the number of cells in series is fixed), and indicates that those BESS configurations may not be the best option for feeding an industrial infrastructure by themselves since, even though technically viable, it is costly.

5. Conclusions

This paper presents a BESS dimensioning methodology for reducing the fixed term of the electricity access fee for industrial consumption, considering battery ageing and the cost of the BESS and electricity access fees. By connecting a BESS together with a consumption, the power demand peaks can be reduced, so there is no need for contracting a high fixed term power to cover the high demand peaks.
A five-step dimensioning methodology is described, finishing with a cost–benefit analysis to facilitate the final decision making. The methodology is easily implemented and can be adapted to different electricity market conditions, as well as particularized to different BESS or load conditions. The parameter that defines the different scenarios of the methodology is the power contracted from the grid, being the decision variable the combined cost of the BESS and the fixed electricity fee.
Results drawn from the two case examples show that implementing a small battery to limit the consumption peaks can lead to considerable cost reduction for the industrial consumer. In fact, the best techno-economical solution corresponds to a small BESS that limits the peak consumption. The low C rate, DoD, and steady temperature experienced by a BESS that only limits the top part of the peak consumption, guarantees a long lifespan that highly reduces the overall yearly costs. Given that BESS are over-dimensioned in energy in several scenarios (S6, S5, W8, W7, and W6), a higher contribution from the BESS could be imposed in order to reduce the fixed power contracted from the grid, achieving a higher peak reduction. However, this leads to an increased ageing (higher C rate, DoD, and temperature profile) that has an impact on the techno-economical decision, turning those solutions into non-optimum.
Apart from the previous conclusion, depending on the case example and scenario under study, it could be beneficial from the economical point of view to increase the size of the BESS with more cells in parallel. This situation occurs when the BESS energy is suited to the BESS energy requirements (scenario S4). This forces the BESS to work with a high DoD and high C rates, deriving in a premature ageing. Thus, increasing the BESS size will allow it to work under less stress, extending the time needed to a BESS replacement and reducing the overall yearly costs.
One important conclusion drawn form the case examples results is that the optimum BESS is over-dimensioned in both power and energy. This may indicate that other energy storage technologies different than Li-ion batteries could be more beneficial from the techno-economic point of view. Supercapacitors, which can last millions of cycles until they need a replacement, or flow batteries, which can dissociate energy and power, may be suitable for their inclusion in a further study. In addition, if the industrial consumption is facing a scenario with low consumption peaks, the optimum solution could be discarding the usage of an energy storage system at all. As previously stated, the presence of high consumption peaks is the reason that justifies the inclusion of a BESS together with the industrial consumption.
Consequently, the proposed methodology is of potential interest for industrial consumers, since the cost-benefit analysis may reduce the yearly cost of their infrastructure, and also for TSOs and DSOs, since the peak reduction improves the efficiency of the transmission and distribution of the energy along the electric power grid. Moreover, BESS manufacturers could also find benefits in this methodology for the development of specific products related to this industrial demand peak and fixed term fee reduction.
Suggested future works include the parametrizations of the grid with frequency and voltage variations, so that further analysis considering BESS contributions to the grid in terms of frequency and voltage regulation can be performed. Moreover, time discrimination pricing can be added to electricity energy prices, so that the BESS can recharge during low price periods, providing an even higher reduction than the one shown in this work. At last, a techno-economic evaluation considering other energy storage technologies such as supercapacitors or flow batteries may result in interesting conclusions.

Author Contributions

Conceptualization, J.N. and M.L.; methodology, J.N., M.B. and G.N.; software, J.N. and M.B.; validation, J.T. and M.B.; formal analysis, J.N.; investigation, J.N.; data curation, M.S.-H., J.T. and M.B.; writing—original draft preparation, J.N.; writing—review and editing, M.S.-H., M.L. and G.N.; visualization, J.N., J.T. and M.S.-H.; supervision, M.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
BESSBattery Energy Storage System
DoDDepth of Discharge
ESSEnergy Storage System
PCCPoint of common coupling
SoCState of Charge
VSCVoltage Source Converter

References

  1. Eurostat, S.E. Electricity Price Statistics. Available online: https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Electricity_price_statistics#Electricity_prices_for_non-household_consumers (accessed on 11 August 2021).
  2. Jardini, J.A.; Tahan, C.M.; Gouvea, M.R.; Ahn, S.U.; Figueiredo, F. Daily load profiles for residential, commercial and industrial low voltage consumers. IEEE Trans. Power Deliv. 2000, 15, 375–380. [Google Scholar] [CrossRef] [Green Version]
  3. Svetozarevic, B.; Begle, M.; Jayathissa, P.; Caranovic, S.; Shepherd, R.F.; Nagy, Z.; Hischier, I.; Hofer, J.; Schlueter, A. Dynamic photovoltaic building envelopes for adaptive energy and comfort management. Nat. Energy 2019, 4, 671–682. [Google Scholar] [CrossRef]
  4. Biyik, E.; Araz, M.; Hepbasli, A.; Shahrestani, M.; Yao, R.; Shao, L.; Essah, E.; Oliveira, A.C.; Del Cano, T.; Rico, E.; et al. A key review of building integrated photovoltaic (BIPV) systems. Eng. Sci. Technol. Int. J. 2017, 20, 833–858. [Google Scholar] [CrossRef]
  5. Niu, J.; Tian, Z.; Lu, Y.; Zhao, H. Flexible dispatch of a building energy system using building thermal storage and battery energy storage. Appl. Energy 2019, 243, 274–287. [Google Scholar] [CrossRef]
  6. Lizana, J.; Chacartegui, R.; Barrios-Padura, A.; Ortiz, C. Advanced low-carbon energy measures based on thermal energy storage in buildings: A review. Renew. Sustain. Energy Rev. 2018, 82, 3705–3749. [Google Scholar] [CrossRef]
  7. e Silva, G.d.O.; Hendrick, P. Pumped hydro energy storage in buildings. Appl. Energy 2016, 179, 1242–1250. [Google Scholar] [CrossRef]
  8. Durand, J.M.; Duarte, M.J.; Clerens, P. European energy storage technology development roadmap towards 2030. Int. Energy Storage Policy Regul Work 2017, 108, 1–128. [Google Scholar]
  9. EASE—Storage Applications. Available online: http://ease-storage.eu/energy-storage/applications/ (accessed on 15 April 2021).
  10. Yassin, M.A.; Kolhe, M.; Sharma, A.; Garud, S. Battery capacity estimation for building integrated photovoltaic system: Design study for different geographical location (s). Energy Procedia 2017, 142, 3433–3439. [Google Scholar] [CrossRef]
  11. Salpakari, J.; Lund, P. Optimal and rule-based control strategies for energy flexibility in buildings with PV. Appl. Energy 2016, 161, 425–436. [Google Scholar] [CrossRef] [Green Version]
  12. Milis, K.; Peremans, H.; Van Passel, S. Steering the adoption of battery storage through electricity tariff design. Renew. Sustain. Energy Rev. 2018, 98, 125–139. [Google Scholar] [CrossRef]
  13. Davis, M.; Hiralal, P. Batteries as a service: A new look at electricity peak demand management for houses in the UK. Procedia Eng. 2016, 145, 1448–1455. [Google Scholar] [CrossRef]
  14. Mulder, G.; Six, D.; Claessens, B.; Broes, T.; Omar, N.; Van Mierlo, J. The dimensioning of PV-battery systems depending on the incentive and selling price conditions. Appl. Energy 2013, 111, 1126–1135. [Google Scholar] [CrossRef]
  15. Jankowiak, C.; Zacharopoulos, A.; Brandoni, C.; Keatley, P.; MacArtain, P.; Hewitt, N. Assessing the benefits of decentralised residential batteries for load peak shaving. J. Energy Storage 2020, 32, 101779. [Google Scholar] [CrossRef]
  16. Pandžić, H. Optimal battery energy storage investment in buildings. Energy Build. 2018, 175, 189–198. [Google Scholar] [CrossRef]
  17. Fotouhi, A.; Auger, D.J.; Propp, K.; Longo, S.; Wild, M. A review on electric vehicle battery modelling: From Lithium-ion toward Lithium–Sulphur. Renew. Sustain. Energy Rev. 2016, 56, 1008–1021. [Google Scholar] [CrossRef] [Green Version]
  18. Zhang, L.; Hu, X.; Wang, Z.; Sun, F.; Dorrell, D.G. A review of supercapacitor modeling, estimation, and applications: A control/management perspective. Renew. Sustain. Energy Rev. 2018, 81, 1868–1878. [Google Scholar] [CrossRef]
  19. Amiribavandpour, P.; Shen, W.; Kapoor, A. Development of thermal-electrochemical model for lithium ion 18650 battery packs in electric vehicles. In Proceedings of the 2013 IEEE Vehicle Power and Propulsion Conference (VPPC), Beijing, China, 15–18 October 2013; pp. 1–5. [Google Scholar]
  20. Rao, V.; Singhal, G.; Kumar, A.; Navet, N. Battery model for embedded systems. In Proceedings of the 18th International Conference on VLSI Design held jointly with 4th International Conference on Embedded Systems Design, Kolkata, India, 3–7 January 2005; pp. 105–110. [Google Scholar]
  21. Lam, L.; Bauer, P.; Kelder, E. A practical circuit-based model for Li-ion battery cells in electric vehicle applications. In Proceedings of the 2011 IEEE 33rd International Telecommunications Energy Conference (INTELEC), Amsterdam, The Netherlands, 9–13 October 2011; pp. 1–9. [Google Scholar]
  22. Tremblay, O.; Dessaint, L.A.; Dekkiche, A.I. A generic battery model for the dynamic simulation of hybrid electric vehicles. In Proceedings of the 2007 IEEE Vehicle Power and Propulsion Conference, Arlington, TX, USA, 9–12 September 2007; pp. 284–289. [Google Scholar]
  23. Fan, L. Control and Dynamics in Power Systems and Microgrids; CRC Press: Boca Raton, FL, USA, 2017. [Google Scholar]
  24. Allègre, A.L.; Trigui, R.; Bouscayrol, A. Different energy management strategies of Hybrid Energy Storage System (HESS) using batteries and supercapacitors for vehicular applications. In Proceedings of the 2010 IEEE Vehicle Power and Propulsion Conference, Lille, France, 1–3 September 2010; pp. 1–6. [Google Scholar]
  25. Laldin, O.; Moshirvaziri, M.; Trescases, O. Predictive algorithm for optimizing power flow in hybrid ultracapacitor/battery storage systems for light electric vehicles. IEEE Trans. Power Electron. 2012, 28, 3882–3895. [Google Scholar] [CrossRef]
  26. Zhou, F.; Xiao, F.; Chang, C.; Shao, Y.; Song, C. Adaptive model predictive control-based energy management for semi-active hybrid energy storage systems on electric vehicles. Energies 2017, 10, 1063. [Google Scholar] [CrossRef] [Green Version]
  27. Yazdani, A.; Iravani, R. Voltage-Sourced Converters in Power Systems; Wiley Online Library: Hoboken, NJ, USA, 2010; Volume 39. [Google Scholar]
  28. Concha, P.M.T. Analysis and Design Considerations of an Electric Vehicle Powertrain regarding Energy Efficiency and Magnetic Field Exposure. Ph.D. Thesis, ETSI Industriales (UPM), Madrid, Spain, 2016. [Google Scholar]
  29. Nájera, J.; Moreno-Torres, P.; Lafoz, M.; De Castro, R.M.; R Arribas, J. Approach to hybrid energy storage systems dimensioning for urban electric buses regarding efficiency and battery aging. Energies 2017, 10, 1708. [Google Scholar] [CrossRef] [Green Version]
  30. Omar, N.; Monem, M.A.; Firouz, Y.; Salminen, J.; Smekens, J.; Hegazy, O.; Gaulous, H.; Mulder, G.; Van den Bossche, P.; Coosemans, T.; et al. Lithium iron phosphate based battery–Assessment of the aging parameters and development of cycle life model. Appl. Energy 2014, 113, 1575–1585. [Google Scholar] [CrossRef]
  31. Shepherd, C.M. Design of primary and secondary cells: II. An equation describing battery discharge. J. Electrochem. Soc. 1965, 112, 657. [Google Scholar] [CrossRef]
  32. Tremblay, O.; Dessaint, L.A. Experimental validation of a battery dynamic model for EV applications. World Electr. Veh. J. 2009, 3, 289–298. [Google Scholar] [CrossRef] [Green Version]
  33. Nájera, J. Study and Analysis of the Behavior of LFP and NMC Electric Vehicle Batteries Concerning Their Ageing and Their Integration into the Power Grid. Ph.D. Thesis, Universidad Politécnica de Madrid, Madrid, Spain, 2021. [Google Scholar]
  34. Saw, L.; Somasundaram, K.; Ye, Y.; Tay, A. Electro-thermal analysis of Lithium Iron Phosphate battery for electric vehicles. J. Power Sources 2014, 249, 231–238. [Google Scholar] [CrossRef]
  35. Chen, Y.; Evans, J.W. Three-dimensional thermal modeling of lithium-polymer batteries under galvanostatic discharge and dynamic power profile. J. Electrochem. Soc. 1994, 141, 2947. [Google Scholar] [CrossRef]
  36. Rao, L.; Newman, J. Heat-generation rate and general energy balance for insertion battery systems. J. Electrochem. Soc. 1997, 144, 2697. [Google Scholar] [CrossRef]
  37. Redondo-Iglesias, E.; Venet, P.; Pelissier, S. Calendar and cycling ageing combination of batteries in electric vehicles. Microelectron. Reliab. 2018, 88, 1212–1215. [Google Scholar] [CrossRef] [Green Version]
  38. Wang, J.; Purewal, J.; Liu, P.; Hicks-Garner, J.; Soukazian, S.; Sherman, E.; Sorenson, A.; Vu, L.; Tataria, H.; Verbrugge, M.W. Degradation of lithium ion batteries employing graphite negatives and nickel–cobalt–manganese oxide+ spinel manganese oxide positives: Part 1, aging mechanisms and life estimation. J. Power Sources 2014, 269, 937–948. [Google Scholar] [CrossRef]
  39. Iglesias, E.R. Étude du Vieillissement des Batteries Lithium-ion Dans Les Applications “Véhicule Électrique”: Combinaison des Effets de Vieillissement Calendaire et de Cyclage. Ph.D. Thesis, Université de Lyon, Lyon, France, 2017. [Google Scholar]
  40. Kokam. SLBP 55Ah High Power Superior Lithium Polymer Battery; Technical Report; Kokam: Siheung, Korea, 2015. [Google Scholar]
  41. Mongird, K.; Viswanathan, V.V.; Balducci, P.J.; Alam, M.J.E.; Fotedar, V.; Koritarov, V.S.; Hadjerioua, B. Energy Storage Technology and Cost Characterization Report; Technical Report; Pacific Northwest National Lab. (PNNL): Richland, WA, USA, 2019. [Google Scholar]
  42. de España, G. Informe de Precios Energéticos Regulados; Technical Report; Instituto para la Diversificación y Ahorro de la Energía (IDAE): Madrid, Spain, 2019. [Google Scholar]
  43. Mongird, K.; Viswanathan, V.; Balducci, P.; Alam, J.; Fotedar, V.; Koritarov, V.; Hadjerioua, B. An evaluation of energy storage cost and performance characteristics. Energies 2020, 13, 3307. [Google Scholar] [CrossRef]
  44. Budes, F.B.; Ochoa, G.V.; Escorcia, Y.C. An Economic Evaluation of Renewable and Conventional Electricity Generation Systems in a Shopping Center Using HOMER Pro®. Contemp. Eng. Sci. 2017, 10, 1287–1295. [Google Scholar] [CrossRef]
  45. Mehta, S.; Basak, P. A case study on pv assisted microgrid using homer pro for variation of solar irradiance affecting cost of energy. In Proceedings of the 2020 IEEE 9th Power India International Conference (PIICON), Sonepat, India, 28 February–1 March 2020; pp. 1–6. [Google Scholar]
Figure 1. Flow chart of the proposed BESS dimensioning methodology.
Figure 1. Flow chart of the proposed BESS dimensioning methodology.
Applsci 11 07395 g001
Figure 2. General model diagram.
Figure 2. General model diagram.
Applsci 11 07395 g002
Figure 3. Industrial consumption model in MATLAB Simulink.
Figure 3. Industrial consumption model in MATLAB Simulink.
Applsci 11 07395 g003
Figure 4. Flow diagram for the VSC high-level control.
Figure 4. Flow diagram for the VSC high-level control.
Applsci 11 07395 g004
Figure 5. VSC low-level control model in MATLAB Simulink.
Figure 5. VSC low-level control model in MATLAB Simulink.
Applsci 11 07395 g005
Figure 6. Battery equivalent circuit model.
Figure 6. Battery equivalent circuit model.
Applsci 11 07395 g006
Figure 7. Industrial consumption profiles for summer and winter scenarios.
Figure 7. Industrial consumption profiles for summer and winter scenarios.
Applsci 11 07395 g007
Figure 8. Cumulative energy consumed by the load in summer and winter scenarios.
Figure 8. Cumulative energy consumed by the load in summer and winter scenarios.
Applsci 11 07395 g008
Figure 9. BESS power profile in summer for different values of P L I M .
Figure 9. BESS power profile in summer for different values of P L I M .
Applsci 11 07395 g009
Figure 10. BESS power profile in winter for different values of P L I M .
Figure 10. BESS power profile in winter for different values of P L I M .
Applsci 11 07395 g010
Figure 11. Days until Q = 20 % as a function of the BESS configuration in summer.
Figure 11. Days until Q = 20 % as a function of the BESS configuration in summer.
Applsci 11 07395 g011
Figure 12. Days until Q = 20 % as a function of the BESS configuration in winter.
Figure 12. Days until Q = 20 % as a function of the BESS configuration in winter.
Applsci 11 07395 g012
Table 1. Grid model parameters.
Table 1. Grid model parameters.
ParameterValue
Reference voltage400 V
Short-circuit ratio25
X/R ratio20
Table 2. Battery model data and parameters [33,40].
Table 2. Battery model data and parameters [33,40].
DataValueRemarks
Reference capacity55 Ah0.2C, 23 °C
ImpedanceMax. 0.60 m Ω AC 1 kHz
Average voltage3.7 V
Lower limited voltage2.7 V
Upper limited voltage4.2 V
ParameterValueParameterValue
a 1.3961 × 10 7 b 7.7116 × 10 5
c 0.0107 d 1.2959 × 10 3
e 0.4404 f 164.7155
g 0.6898 h 4.2126 × 10 3
z 0.5
Table 3. Scenarios defined for the case example.
Table 3. Scenarios defined for the case example.
Scenario P LIMIT
SB70 kW
S660 kW
......
S220 kW
S110 kW
WB90 kW
W880 kW
......
W220 kW
W110 kW
Table 5. Summarized costs.
Table 5. Summarized costs.
ItemCost
-[€/kW and Year]
P159.1734
P239.4906
P38.3677
Table 7. Costs for the summer scenarios.
Table 7. Costs for the summer scenarios.
Scenario P LIMIT BESS Config.Fixed Access FeeBESS ProjectTotal Cost
-[kW]-[€/Year][€/Year][€/Year]
SB90-7492.2-7492.2
S66013s1p6421.9940.37362.2
+1p 989.87411.7
+2p 1039.77461.6
+3p 1089.67511.5
S55013s1p5351.620747425.6
+1p 2118.37469.9
+2p 2167.57519.1
+3p 2217.17568.7
S44013s1p4281.332917572.3
+1p 3265.57546.8
+2p 3305.57586.8
+3p 3351.67632.9
S33013s14p32116098.59309.5
+1p 6141.69352.6
+2p 6185.99396.9
+3p 6231.19442.1
Table 8. Costs for the winter scenarios.
Table 8. Costs for the winter scenarios.
Scenario P LIMIT BESS Config.Fixed Access FeeBESS ProjectTotal
-[kW]-[€/Year][€/Year][€/Year]
WB90-9632.9-9632.9
W88013s1p8562.5525.19087.6
+1p 574.99137.4
+2p 624.89187.3
+3p 674.79234.2
W77013s1p7492.21654.69146.8
+1p 1702.69194.8
+2p 1752.29244.4
+3p 18029294.2
W66013s1p6421.92802.59224.4
+1p 2833.49255.3
+2p 2881.39303.2
+3p 2930.59352.4
W55013s5p5351.64487.79839.3
+1p 4523.99875.5
+2p 45659916.6
+3p 4609.19960.7
W44013s19p4281.3746011,741.3
+1p 750911,790.3
+2p 7554.711,836
+3p 7601.411,882.7
W33013s39p321111,22414,435
+1p 11,27114,482
+2p 11,31914,530
+3p 11,36714,578
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Nájera, J.; Santos-Herran, M.; Blanco, M.; Navarro, G.; Torres, J.; Lafoz, M. Battery Energy Storage System Dimensioning for Reducing the Fixed Term of the Electricity Access Rate in Industrial Consumptions. Appl. Sci. 2021, 11, 7395. https://0-doi-org.brum.beds.ac.uk/10.3390/app11167395

AMA Style

Nájera J, Santos-Herran M, Blanco M, Navarro G, Torres J, Lafoz M. Battery Energy Storage System Dimensioning for Reducing the Fixed Term of the Electricity Access Rate in Industrial Consumptions. Applied Sciences. 2021; 11(16):7395. https://0-doi-org.brum.beds.ac.uk/10.3390/app11167395

Chicago/Turabian Style

Nájera, Jorge, Miguel Santos-Herran, Marcos Blanco, Gustavo Navarro, Jorge Torres, and Marcos Lafoz. 2021. "Battery Energy Storage System Dimensioning for Reducing the Fixed Term of the Electricity Access Rate in Industrial Consumptions" Applied Sciences 11, no. 16: 7395. https://0-doi-org.brum.beds.ac.uk/10.3390/app11167395

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop